Timeline

Winter 2021

Funding awarded

The Department of Neighborhood Development approved funding for this project.
Winter 2021

City Planning

This project is going through a zoning review with the Boston Planning and Development Agency (BPDA). Then we’ll work with the Developer on funding, design, and compliance.

Under Construction

Predicted Date: Fall 2022

Project Complete

Predicted Date: Fall 2024