Cummins Highway Construction Update: September 2025

Through September, we will continue installing new curb and green infrastructure from Greenfield Road/Weybosset Street to Woodhaven Street.  

Major work on the project between the Wood Avenue/Harvard Street intersection and Woodhaven Street is planned to wrap up this fall. In this segment, major elements of the street are now taking shape.

Green infrastructure is a term for stormwater management that uses natural materials to remove pollutants and absorb water back into the ground.  On Cummins, these areas will have a subsurface layer of permeable rock material and raised drains to absorb stormwater.

September 1, 2025 - September 5, 202
  • Construction activity will be temporarily paused on Monday, 9/1 (Labor Day) and from Thursday 9/4 to Tuesday, 9/9
  • Install curb at roundabout
  • Install curb between Bismarck Street and Woodhaven Street
  • Begin installing curb between Corman Street and Itasca Street
  • Continue pouring cement for driveways between Wood/Harvard and Itasca
September 8, 2025 - September 12, 2025
  • Install curb between Ridlon Road and Rugby Road
  • Continue pouring cement for driveways between Itasca Street and Woodhaven Street
  • Begin paving bike lane from Itasca Street to Woodhaven Street
September 15, 2025 - September 19, 2025
  • Install curb between Ridlon Road and Rugby Road
  • Begin paving bike lane from Itasca Street to Woodhaven Street