city_hall

Official websites use .boston.gov

A .boston.gov website belongs to an official government organization in the City of Boston.

lock

Secure .gov websites use HTTPS

A lock or https:// means you've safely connected to the .gov website. Share sensitive information only on official, secure websites.

Boston.gov Search

Get direct answers to your questions about City of Boston services. While we strive for accuracy, our search can occasionally provide unexpected results. You can help us improve by using the feedback buttons below each answer. Have questions? Contact us at digital@boston.gov.

Questions? Contact us at digital@boston.gov.

Choose a search type

Cummins Highway Construction Update: July 2025

Construction hours: 7:00 a.m. to 3:30 p.m.

Below is a summary of the primary construction activities for the next few weeks. This schedule is subject to change based on weather conditions and other factors.

Planned work  7/7 - 7/11
  • Forming and installing sidewalks from Hebron St. to Livermore S.
  • Installing curb and pedestrian ramps around the Greenfield/ Weybosset Area
  • Continue placing recessed planter soil between Wood Ave and Weybosset St
Planned work 7/14 - 7/18
  • Installing curb from Hebron St to Livermore St
  • Installing curb and pedestrian ramps around the Weybosset Corner towards Livermore St
  • Installing rotary island curb and concrete
Planned work 7/21 - 7/25
  • Forming and installing sidewalks from Livermore St to Weybosset St
  • Installing curb from Livermore St to Weybosset St
  • Finishing rotary island curb and concrete

     