Various Courts Citywide

Court renovations are underway this spring at eight Boston Parks.

Have questions? Contact:

Project Phase

timeline-graphic
timeline-graphic
timeline-graphic
timeline-graphic
timeline-graphic
Pending
Planning
Design
Construction
Complete
Construction is expected to be complete by July.

Project Information

Locations
Ross Playground Hyde Park 02136
Hunt Playground Mattapan 02126
Mozart Street Playground Jamaica Plain 02130
Rogers Park Allston 02135
East Boston Memorial Park I East Boston 02128
Orton Field South Boston 02127
Ripley Playground Dorchester 02121
Thetford Evans Playground Dorchester 02124
See all
Project Features
Basketball
Multi-Use Court
Tennis
See all
Expected Year to be Completed
2026
Project Manager
Kezia Ofiesh
Consultant
Weston & Sampson
Contractor
Lawrence-Lynch Corporation
Primary Project Type
Parks and Green Space

For the spring 2026 construction season, we are undertaking improvements to the basketball and tennis courts, as well as a new Bike Town, at eight different sites. Work is expected to be complete by July.

  • East Boston Memorial Park (tennis)
  • Hunt-Almont Playground (tennis)
  • Mozart Street Playground, Jamaica Plain (basketball)
  • Orton Field, South Boston (basketball)
  • Ripley Playground, Dorchester (basketball)
  • Rogers Park, Allston-Brighton (basketball and tennis)
  • Ross Playground, Hyde Park (basketball, tennis, and bike town)
  • Thetford Evans Playground (basketball and tennis)