Improvements To Harambee Park

Implementation of a multi-phased park renovation project. Features a new playground on the west side of the park, pathway, and lighting improvements throughout the park, and sports facility improvements.

Have questions? Contact:

Project Phase

Pending
Planning
Design
Construction
Complete
Phase 4 is anticipated to be complete by mid-April 2025. Phase 5 design will begin in summer 2025

Project Information

Location
930 Blue Hill Avenue Dorchester 02124
See all
Project Features
Pathway Improvements
Sports fields and courts
See all
Expected Year to be Completed
2025
Project Manager
Amy Linné
Consultant
Weston and Sampson
Contractor
Fleming Brothers, Inc.
Project Type
Parks and Green Space

Harambee Park, formerly Franklin Field, is an active recreation park with 45 acres of fields for a variety of sports. The park contains basketball courts, cricket pitches, multi-purpose soccer and lacrosse fields, a football field, little league field and play spaces. Boston Parks and Recreation completed a master plan in early 2016. The plan keeps the existing recreational uses, re-orients the fields for optimum solar orientation, adds pathways with pedestrian lighting, and introduces a new play area on the west side of the park along Blue Hill Avenue.

Timeline
  • Construction of Phase 1 (the new play space, basketball courts, and entrances) was completed in 2018.
  • Construction of Phase 2 (multi-purpose soccer and lacrosse fields, and pathways) was completed in 2021.
  • Construction of Phase 3 (football field and practice field) was completed in 2022.
  • Construction of Phase 4 (cricket competition field and practice field) has begun as of November 2023 and will be completed late summer / early fall 2024, with another year for the turf establishment period.

The construction budget is $2,083,000.

Harambee Park Phase 4 diagram

Project information

Westview Street CRICKET FIELDS
  • Project Status: Under Construction
  • Construction Budget: $2,083,000
  • Project Features: Two cricket fields (one competition field with lighting, one practice field), bleacher seating, pathways and pedestrian lighting
  • Consultant: Weston & Sampson Engineers, Inc.
  • Contractor: Fleming Brothers Inc.
Westview Street Football Field
  • Project Status: Complete
  • Construction Budget: $2,600,000
  • Project Features: Football field improvements, pathway, and entry improvements
  • Consultant: Weston & Sampson Engineers, Inc.
  • Contractor: Fleming Brothers Inc.
Talbot Avenue Multipurpose Fields
  • Project Status: Complete
  • Construction Budget: $3,060,000
  • Project Features: Soccer and Lacrosse fields, pathway and lighting improvements, entrance enhancement
  • Consultant: Weston & Sampson Engineers, Inc.
  • Contractor: Fleming Brothers Inc.
Blue Hill Avenue Playground and Courts
  • Project Status: Complete
  • Construction Budget: $2,500,000
  • Project Features: New playground, court renovation with lights, pathway, and entry improvements
  • Consultant: Weston & Sampson Engineers, Inc.
  • Contractor: Fleming Brothers Inc.

Upcoming meetings

Meetings

Community meetings archive

We place information on upcoming and previous meetings in the public notices section of Boston.gov. We'll update this page with new meeting information as we get it.

Phase 3: Football Field and Walkways on Westview Street
Phase 2: Multipurpose Fields and Walkways on Talbot Avenue
Phase 1: New Playground and Basketball Courts on Blue Hill Avenue

Harambee Park Master Plan and Implementation Phases

Past Process

A Master Plan was drafted in 2015 to inform future phases park improvements. A preferred site plan option was developed with community input and an eye to future open space need.

The scope of Phase 1 included:

  1. Basketball court improvements with new sports lighting.
  2. An exciting new play area on Blue Hill Avenue. The play area features a fully accessible mound and play tower, hill slides, climbing equipment, swings, and water play.
  3. Pathway and entry improvements to improve safety.

The scope of Phase 2 included:

  1. Improved multipurpose fields for Soccer and Lacrosse.
  2. Green infrastructure improvements to better control wet areas and drainage.
  3. Pathway and entry improvements to improve safety.