John J. Ryan Playground Improvements

The first phase of construction is underway at Ryan Playground, and the second phase is scheduled to begin at the end of fall 2025. Installing the berm, a critical new piece of infrastructure, will protect the park and Charlestown from sea level rise.

Sign up for project updates!
Have questions? Contact:

Project Phase

timeline-graphic
timeline-graphic
timeline-graphic
timeline-graphic
timeline-graphic
Pending
Planning
Design
Construction
Complete

Project Information

Location
Ryan Playground Charlestown 02129
See all
Project Features
Accessibility
Community engagement
Demolition and construction
Green infrastructure
Infrastructure improvements
Landscaping
Mobility
Passive Use
Pathway Improvements
Playground
Resiliency
Sports fields and courts
Sustainability
Water Play
See all
Expected Year to be Completed
2026
Primary Project Type
Parks and Green Space

Our contractor is busy installing the micropiles and ground improvements that will support the structure of the berm along the Mystic edge. We will be posting construction updates below on a monthly basis. 

  • Project Features: Little league, multi-use field, passive use, playground and water play.
  • Budget: First Phase: $6.7 million; Second Phase: $16 million
  • Consultant: Weston and Sampson
  • Contractor: First Phase: Unified Construction, Inc.; Second Phase: Fleming Bros. Inc.

Micropile Installation